Cable Trays
Learn how to draw cable trays and route cabling through them in Hamina Network Planner Plus.
Adding cable trays requires a Hamina Network Planner Plus license.
Cable trays enable routing cables more closely to the paths they they will follow on site, rather than straight lines drawn across the map. Devices near a tray have their cables automatically routed through it, which makes cable schedules and length estimates much closer to what will really be installed.
Drawing Cable Trays
Cable trays are drawn exactly like walls: as a chain of straight segments. To draw cable trays:
Select the Cable Trays tool in the toolbar.
Left-click on the map to start a tray segment.
Left-click again to place the other end of the segment.
Continue left-clicking to chain additional segments together, following the real path of the tray.
Right-click to stop drawing.
While drawing, hold down the Space bar and move the mouse to pan the map without needing to click.
Editing Cable Trays
Cable trays can be moved and split just like walls:
Move: Switch to the Edit tool, select the tray, and drag it to a new position.
Split: With the Edit tool active, select the tray, then hover over it until the add-point cursor appears, and click to add a point. This lets you reshape a run or branch it in a new direction.
Delete: Select the tray (or a segment of it) with the Edit tool and press Delete/Backspace.
Magnet Distance
Each tray network has a magnet distance, controlled by a slider, which determines how close a device needs to be to get pulled into the tray for cable routing. On the map, this is shown as a shaded blue area surrounding the tray. Any AP, switch, or wired client that falls inside that shaded area is "sucked into" the tray network.
Widening the slider captures devices farther from the tray; narrowing it means only devices very close to the tray will route through it.
How Network Routing Works
Once a device is captured by a tray's magnet distance, Hamina routes its cable through the connected tray network toward its switch. These cables are drawn on the map as dashed lines, and are created automatically for:
Access point to switch
Wired client to switch
Switch to switch
Hamina doesn't force a tray route that's less efficient than a direct one. If the shortest path to the assigned switch lies outside the tray network, Hamina uses that direct path instead of forcing the cable through the trays.
Which switch a device's cable is routed to depends on its switch assignment: either the automatically-selected nearest switch, or a specific switch you've assigned it to. The cable trays only affect how the cable gets there, not which switch it terminates at.
Switch Assignment
By default, switches and wired clients connect to whichever eligible switch is nearest; Hamina picks this automatically. You can override this by forcing a device to connect to a specific switch instead, even one on a different floor, which is useful for matching a planned IDF/MDF layout, balancing port or PoE usage, or modeling redundancy.
Select the device, then in the Edit pane, set its Ethernet connection to the specific switch you want it to use rather than Nearest device.
Cable Length Calculations
Because routing through a tray follows a more predictable, real-world path, Hamina applies different slack to cable length estimates depending on whether a run uses a tray:
Runs routed through a cable tray receive 10% slack
Runs outside cable trays receive 20% slack